Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to (  ) progress.
A. analyze
B. track
C. level
D. extend

参考答案:B(仅供参考) 收藏

【解析】

普通会员无法查看试题解析。[开通试题解析服务]