Your project is behind schedule due to conflict between team members .Haring resolved the conflict, to get the project back on schedule,you should consider ( ).
A、crashing the Schedule
B、performing resource leveling
C、conducting reverse resource allocation Scheduling
D、utilizing the critical chair resources

参考答案:A(仅供参考) 收藏

【解析】