JRS直播试题内容
JRS直播 导航

试题内容

The process of(  )schedule activity durations uses information on schedule activity scope of work, required resource types, estimated resource quantities, and resource calendars with resource availabilities.
A.estimating
B.defining
C.planning
D .sequencing

参考答案:A(仅供参考) 收藏

【解析】

普通会员无法查看试题解析。[开通试题解析服务]