未指定试题:projectxis60%completed,behindscheduleAND

2020年03月19日

试题来源:JRS直播 作者:cnitpm

试题分类:未指定

Project X is 60% completed, behind schedule and over budget. The sponsor has withdrawn funding due other higher priority projects and the department manager has reassigned all team members to Project Y. What should the project manger do?
A、Revise the project management plan to reflect the change in scope
B、Meeting for Project Y
C、Document and archive lessons learned on Project X
D、Calculate the EAC and ETC for the Project X