JRS直播章节习题

导航

英语试题:thedeliveryofaninventorymanagementsystem

2018年09月06日

试题来源:JRS直播 作者:cnitpm

试题分类:英语

The delivery of an inventory management system is being subcontracted based on the value of US$4,000,000. During deployment of the system, it cannot meet the quality requirements. The test needs extra time and money to be done. Which of the following process could contain additional testing and evaluation to provide US$20,000 ?
A、Risk Management Plan
B、Resource Management Plan
C、Change Management Plan
D、Quality management plan

试题出处:http://www.ruantiku.com/shiti/3381613867.html
在下面提交答题后即可查看答案与考友试题分析

温馨提示:因考试政策、内容不断变化与调整,JRS直播提供的以上信息仅供参考,如有异议,请考生以权威部门公布的内容为准!

分享至:

JRS直播 - 信息系统项目管理专业网站

下载APP-在线学习