JRS直播章节习题

导航

英语试题:aprojecthascomplexdependenciesbetweenact

2018年03月06日

试题来源:JRS直播 作者:cnitpm

试题分类:英语

A project has complex dependencies between activities. The activities are assigned to reach in different departments. There is a lack of skilled resources and the company experiences financial issues. Senior management does not address the prioritization of projects. Which of the following risk categories should the project manager consider when develop risk management plan?
A. Project management.
B. Technical
C. Organizational
D. External.

试题出处:http://www.ruantiku.com/shiti/3372617079.html
在下面提交答题后即可查看答案与考友试题分析

温馨提示:因考试政策、内容不断变化与调整,JRS直播提供的以上信息仅供参考,如有异议,请考生以权威部门公布的内容为准!

分享至:

JRS直播 - 信息系统项目管理专业网站

下载APP-在线学习