试题1
A project manager is working on an internal project that requires a new point of sale(POS)transaction system.The project manager discovers an issue with the system that may not only delay this project,but also a number of other projects dependent upon this system. This issue was not include in the risk register,because previous trials deemed the system free o f flaws Who should the project manager contact about this is sue?查看答案
试题参考答案:A
试题解析与讨论:www.fzyzx.cn/st/4808919763.html
试题2
一家产品开发公司正在从事一种消费品的工作。在sprint执行期间,一名关键干系人无法提供反馈。团队应在什么时候收集这名干系人的反馈?查看答案
试题参考答案:C
试题解析与讨论:www.fzyzx.cn/st/529009266.html
试题3
During the last week of the project,a strong storm causes damage and impacts the project's delivery date ?What should t he project manager do查看答案
试题参考答案:A
试题解析与讨论:www.fzyzx.cn/st/4789310256.html
试题4
在规划范围管理过程中,你可以使用以下技术来推动本过程的实现,除了:查看答案
试题参考答案:D
试题解析与讨论:www.fzyzx.cn/st/4244117800.html
试题5
The project has more than 1,000 work packages, and is two years long. It is performing with CPI=1.18 and SPI=0.88. What technique should the project manager use to solve this situation?查看答案
试题参考答案:C
试题解析与讨论:www.fzyzx.cn/st/4939016041.html
试题6
项目每日站会时间很长,经常超过两个小时。项目团队利用站会对项目障碍的解决方案进行扩展讨论。项目经理应该做什么来改善每日站会?查看答案
试题参考答案:D
试题解析与讨论:www.fzyzx.cn/st/5265427763.html
试题7
经过严格质量控制之后,产品满足标准。运营部门请求添加多个新功能,并认为这些新功能很容易实施。但是,添加这些新功能将延迟项目,并导致成本超支。为了管理运营相关方的期望,并提供进度和成本透明度,项目经理应该怎么做?查看答案
试题参考答案:B
试题解析与讨论:www.fzyzx.cn/st/484392857.html
试题8
A project manager receives contradictory input from some stakeholders regarding a project's pros and cons. This impacts other stakeholders’ levels of support and understanding of how the project will benefit the organization. What should the project manager do to align stakeholders' opinions and obtain their active participation?查看答案
试题参考答案:A
试题解析与讨论:www.fzyzx.cn/st/4939821373.html
试题9
关于目标与可交付成果,哪一个更准确:查看答案
试题参考答案:B
试题解析与讨论:www.fzyzx.cn/st/423128601.html
试题10
负责测试报告的敏捷团队成员在每次迭代结束时都没有足够的时间确保可交付成员的质量。敏捷项目经理应该怎么做?查看答案
试题参考答案:D
试题解析与讨论:www.fzyzx.cn/st/5298727321.html