2013年11月11日来源:JRS直播 作者:cnitpm
2013下半年信息系统项目管理师综合知识真题75:The intention of the()is to schedule, organize and control all activities to achieve the project goal eventually.no matter how difficult it is and what kind of risks are there.
75、The intention of the()is to schedule, organize and control all activities to achieve the project goal eventually.no matter how difficult it is and what kind of risks are there.
A、project work breakdown
B、project security authentication
C、project management
D、project flowchart
参考答案:C
JRS直播解析:https://www.fzyzx.cn/pm/9325.html
欢迎大家在评论里给出你的答案,参与讨论
2013下半年信息系统项目管理师综合知识真题汇总:https://www.fzyzx.cn/pm/7732.html
温馨提示:因考试政策、内容不断变化与调整,JRS直播提供的以上信息仅供参考,如有异议,请考生以权威部门公布的内容为准!
相关推荐
2013/11/11
2013/11/11
2013/11/11
2013/11/11
2013/11/11