JRS直播综合知识
JRS直播 - 综合知识 导航

英语复习:The earned value technique is a commonly used method of performance measurement.

2013年10月17日来源:JRS直播 作者:cnitpm

The earned value technique is a commonly used method of performance measurement. It integrates project scope, cost, and schedule measures to help the project management team assess project performance. If a project’s Schedule Performance Index(SPI=EV/PV) value less than 1.0, it means that   ).
 A、the project is ahead of its planned schedule
 B、less work was completed than was planned
 C、the cost overrun for work completed
 D、the cost under-run of performance to date
挣值技术是一种通用的绩效测量方法。它将项目范围、成本、进度整合在一起,帮助项目管理团队评估项目绩效。SPI值若小于1则表示实际进度落后于计划进度。
earned value technique:挣值技术
performance measurement:绩效测量
integrates:整合
scope:范围
cost:成本
schedule:进度
project management team:项目团队
assess:评估
project performance:项目绩效
Schedule Performance Index(SPI=EV/PV):进度执行(绩效)指标
less than:小于
ahead:超前
overrun:超支

温馨提示:因考试政策、内容不断变化与调整,JRS直播提供的以上信息仅供参考,如有异议,请考生以权威部门公布的内容为准!

分享至:

JRS直播 - 信息系统项目管理专业网站

下载APP-在线学习