JRS直播公众号
JRS直播订阅号
The Estimate Activity Resource process is closely coordinated with the( )process.A. Estimate Costs B. Sequence ActivitiesC. Plan Communications D. Conduct Procurements
JRS直播参考答案:A(仅供参考,欢迎评论交流) 收藏
考试信息推送
免费在线答题
优惠报班活动
直播录播辅导