71、The ETL technology is mainly used in ( ) stage.
A、 data collection
B、 data storage
C、 data management
D、 data analysis
JRS直播参考答案:A
查看解析:
www.fzyzx.cn/st/4536424355.html
72、( ) is not used on perception layer of Internet of Things.
A、 WLAN
E、RFID
C、 Bluetooth
D、 SOA
JRS直播参考答案:D
查看解析:
www.fzyzx.cn/st/453657081.html
73、The ( ) is a hierarchical decomposition of the total scope of work to be carried out by the project team to accomplish the project objectives and create the required deliverable.
A、 OBS
B、 WBS
C、 RBS
D、 RAM
JRS直播参考答案:B
查看解析:
www.fzyzx.cn/st/4536610163.html
74、( ) is a measure of schedule performance expressed as the difference between the earned value and the planned value.
A、 Schedule variance (SV)
B、 Cost variance (CV)
C、 Actual cost (AC)
D、 Earned value (EV)
JRS直播参考答案:A
查看解析:
www.fzyzx.cn/st/4536728405.html
75、( ) information is not disclosed to unauthorized individuals.
A、 Authenticity
B、 Integrity
C、 Availability
D、 Confidentiality
JRS直播参考答案:D
查看解析:
www.fzyzx.cn/st/4536821723.html
温馨提示:因考试政策、内容不断变化与调整,JRS直播网站提供的以上信息仅供参考,如有异议,请以权威部门公布的内容为准!
JRS直播致力于为广大信管从业人员、爱好者、大学生提供专业、高质量的课程和服务,解决其考试证书、技能提升和就业的需求。
JRS直播软考课程由JRS直播依托10年专业软考教研倾力打造,教材和资料参编作者和资深讲师坐镇,通过深研历年考试出题规律与考试大纲,深挖核心知识与高频考点,为学员考试保驾护航。面授、直播&录播,多种班型灵活学习,满足不同学员考证需求,降低课程学习难度,使学习效果事半功倍。