Project manager believes that modifying the project scop may provide added value for the customer.The project manager should(    ).
A.change the scope baseline
B.contact the customer to determine if the change adds value
C.call a meeting of the change control board
D.change the project's objectives

参考答案:B(仅供参考) 收藏

【解析】

普通会员无法查看试题解析。[开通试题解析服务]