JRS直播试题内容
JRS直播 导航

试题内容

Project manager realizes that the development cost is Already over budget, The project manager should()
A.stop the development
B.tailor the scope of the Project
C.accept the budget And continue the development
D.submitA change request
参考答案:D(仅供参考) 收藏

【解析】

普通会员无法查看试题解析。[开通试题解析服务]