In (),the project scope,time,and cost are determined in the early phases of the life cycle.Any changes to the scope are carefully managed.
A.predictive life cycle
B.iterative life cycle
C.incremental life cycle
D.adaptive life cycle
参考答案:A(仅供参考) 收藏