The(  )is a hierarchical decomposition of the total scope of work to be Carried out by the project team to accomplish the project objectives and create the required deliverables.
A、project scope statement
B、work package
C、WBS
D、project scope plan
参考答案:C(仅供参考) 收藏

【解析】