Two months into a designed project, the customer requested a modification to the project. The change was made without notify the project manager. During the final testing phase, result were different from what was planned for, This scenario is an example of which of following?
A、Poor definition of the test plan
B、Poor development of quality management
C、Poor use of scope change control
D、Poor adherence to the communication plan